Monday 16 May 2011

WEEK 7 Floor joists

FLOOR JOIST
The floor joists are sorted from the packet to see if the right lengths and quantity were delivered to site. The joist packet allowed for H3.2 joist in the kitchen.

Mark joist to plan and consider where walls land and service pipes will be ie. Toilet and shower waste pipes.
How do we provide a service area if a joist is in the way of a waste pipe?

No comments:

Post a Comment